Doubleview Gold Corp Extends Mineralization East of 2024 Conceptual Pit and Identifies Deeper Porphyry Indicators at Hat Project by Drilling 992m of 0.29% CuEq in hole H101

by Doubleview | Dec 16, 2025 | 2025, Cobalt, Copper, Gold, Hat Project, News, Scandium

Doubleview Gold Corp. (“Doubleview” or the “Company”) is pleased to report assay results from drill holes H100 and H101, completed as part of the 2025 drill program at its 100%-owned Hat Polymetallic Deposit in northwestern British Columbia.

Drill holes H100 and H101 were designed to test eastern extensions of mineralization beyond the 2024 conceptual pit shell, while also evaluating depth continuity and metal zonation within the Hat porphyry system. Results from both drill holes confirm broad, continuous copper-gold-cobalt-scandium mineralization and, when integrated with drill holes announced earlier in 2025, define an expanded mineralization envelope at the Hat Deposit. Assay results from drill holes H102 to H108 will be released when received from the Lab and reviewed and confirmed by our technical team.

Key Highlights

  • Mineralization extended eastward beyond the 2024 conceptual pit outline, supported by long, continuous intercepts in both H100 and H101.
  • H100 intersected 497.0 m of mineralization (129.0–626.0 m) averaging 0.27% CuEq (excluding ScO), confirming continuity into previously under-tested areas east of the 2024 conceptual pit.
  • Elevated cobalt values at depth in H100 may be indicative of proximity to deeper portions of the porphyry system based on observed metal associations at Hat.
  • H101 returned 992.4 m of continuous mineralization, with multiple higher-grade intervals and a higher gold-to-copper ratio relative to the established average of the Hat deposit.
  • Deeper part of the Hat porphyry system remain untested by drilling,
  • Drill holes H100 and H101 at the bottom are more than 500m apart.

Drill Hole H100

  • 497.0 m (129.0–626.0 m) averaging 0.27% CuEq, including:
    • 239.8 m at 0.30% CuEq
    • 141.0 m at 0.31% CuEq
    • 106.2 m at 0.35% CuEq
    • 73.0 m at 0.44% CuEq

Drill hole H100 confirms that mineralization extends eastward beyond the 2024 conceptual pit boundary and remains continuous over substantial thicknesses. The presence of elevated cobalt values within deeper intervals is interpreted by the Company as a potential vector toward deeper parts of the porphyry system. While the significance of this association continues to be evaluated, cobalt enrichment has consistently occurred alongside stronger copper-gold mineralization in several areas of the Hat deposit.

Drill Hole H101

  • 992.4 m (7.5–999.9 m) averaging 0.29% CuEq, including:
    • 618.0 m at 0.37% CuEq
    • 153.0 m at 0.52% CuEq
    • 91.0 m at 0.72% CuEq
    • 32.0 m at 1.26% CuEq
    • 11.2 m at 2.80% CuEq

Drill hole H101 is notable for its higher gold-to-copper ratio compared to the broader Hat deposit average. Such metal ratios are commonly observed within zoned porphyry systems and may reflect variations in metal distribution at different structural or vertical levels. Together with the observed continuity of mineralization from near surface to the end of the drill hole, adds an important new constraint to the evolving geological interpretation of the Hat system. Table 1 tabulates the assay results of H100 and H101.

Table 1: Drill holes H100 and H101 assay results:

Notes:                         

1 – Copper Equivalent (CuEq) currently does not include Scandium

2 - The intervals presented in this table are not true widths.  The true width of mineralized sections has not been determined.

3 – Metal equivalents should not be relied upon for future evaluations.  Drill hole intercepts included in this news release are core lengths that may or may not represent true widths of mineralization. It is not possible to determine true widths.

4 – Parameters used to calculate Copper Equivalent: Au price (US$/oz): 2365.09; Ag price (US$/oz): 27.43; Cu price (US$/lb): 4.17; Co price (US$/lb): 14.76. Au recovery: 89.0%; Ag recovery: 68.0%; Cu recovery: 84.0%; Co recovery: 78.0%. * Copper Equivalent Calculation CuEq in % = ([Ag grade in ppm] *27.43*0.68/31.1035 + [Au grade in ppm] *2365.09*.89/31.1035 + 0.0001* [Co grade in ppm] *14.76*0.78*22.0462 + 0.0001* [Cu grade in ppm] *4.17*0.84*22.0462)/(4.17*22.0462*0.84).

Details of the algorithm used to estimate %CuEq are presented in the notes above. The metal values used in our current algorithm are average trailing three years commodity prices, and do not reflect recent dramatic increases in prices of mineral commodities. Scandium, a potentially recoverable high value strategic alloy metal (customarily quoted as Sc2O) that is present in small but possibly highly important amounts in Hat mineralization, is not assigned any value pending metallurgical investigations and recoverable results. 

Core samples are delivered securely to a fully accredited commercial laboratory and processed by industry-standard methods.  Assays are received at irregular intervals, verified by reference to notes provided by our field crew, added to our database, and disseminated publicly by News Release.   

Figure 1: Plan view showing 2025 drill hole locations relative to the 2024 conceptual pit outline, highlighting eastward extensions of mineralization

Drill hole From (m) To (m) Length (m) Ag (g/t) Au (g/t) Co (g/t) Cu (%) Sc2O3(g/t) CuEq (%) excl Sc2O3
H100 129.0 626.0 497.0 0.13 0.14 74.44 0.12 40.3 0.27
Inc. 195.0 434.8 239.8 0.11 0.18 91.44 0.12 40.2 0.30
Inc. 195.0 336.0 141.0 0.10 0.21 88.15 0.10 44.8 0.31
Inc. 195.0 301.2 106.2 0.12 0.25 85.31 0.11 43.8 0.35
Inc. 195.0 268.0 73.0 0.14 0.33 86.47 0.12 35.7 0.44
H101 7.5 999.9 992.4 0.17 0.14 64.5 0.15 43.2 0.29
Inc. 273.0 891.0 618.0 0.20 0.17 67.72 0.20 44.2 0.37
Inc. 273.0 426.0 153.0 0.31 0.21 129.29 0.30 36.2 0.52
Inc. 273.0 364.0 91.0 0.45 0.28 148.85 0.43 35.2 0.72
Inc. 276.0 690.4 414.4 0.20 0.19 75.73 0.20 42.6 0.39
Inc. 578.0 589.2 11.2 0.42 1.70 84.6 1.28 47.3 2.80
Inc. 791.0 936.0 145.0 0.23 0.20 59.01 0.24 50.3 0.44
Inc. 858.0 890.0 32.0 0.73 0.58 112.7 0.71 48.0 1.26
WordPress Table Plugin

Figure 2: Cross-section illustrating continuity of mineralization at depth and beyond the eastern margin of the conceptual pit.

Geological Interpretation

Results from drill holes H100 and H101, when combined with data from drill holes reported earlier in the 2025 season, define an expanded mineralization envelope at the Hat Deposit. Mineralization now demonstrably extends eastward beyond the conceptual pit shell, continuous to depths approaching one kilometre and supports the interpretation of a large, vertically extended porphyry system.

The identification of cobalt-enriched intervals at depth in H100 and the gold-rich character of H101 provide additional geological vectors that may assist in defining future drill targets. Importantly, the deepest portions of the Hat porphyry system have not yet been tested by drilling; the Company considers these areas a priority for future exploration programs.

Farshad Shirvani, President and CEO of Doubleview Gold Corp., commented:

“Drill holes H100 and H101 represent an important step forward in our understanding of the Hat system. These holes confirm that mineralization continues east of the 2024 conceptual pit, as proposed in MRE-1 and remains robust at depth. The elevated cobalt values encountered in H100, together with the higher gold-to-copper ratios observed in H101, provide valuable geological insight into the internal zonation of the system.

Together with our large database, including drill results announced earlier this year, these holes collectively expand the mineralization envelope and reinforce our interpretation of Hat as a large, vertically extensive porphyry system. The deepest parts of the system remain untested, and we believe the results to date strongly justify continued, disciplined exploration focused on depth and lateral extensions.”

Figure 3: 2024 Conceptual pit shell in 3D and 2025 drill holes demonstrating the strategic exploration in 2025

Figure 4: Three-dimensional views of the 2024 conceptual pit shell with 2025 drill holes, demonstrating strategic targeting of depth and lateral extensions within the Hat porphyry system.

Figure 5: Three-dimensional views of the 2024 conceptual pit shell with 2025 drill holes, demonstrating strategic targeting of depth and lateral extensions within the Hat porphyry system.

Table 2 summarizes coordinates of the recent drill holes.

Table 2.  Details of Location and direction of drill holes:

DDH ID UTM-East (m) UTM-North (m) Elevation (m) Dip (°) Azimuth (°) Max-Depth (m) Year
H100 348203.0 6453897.0 972 -61.1 120 840.0 2025
H101 348203.0 6453897.0 966 -75.0 120 1015.5 2025
WordPress Table Plugin

Quality Assurance and Quality Control:

Hat Project drill cores are processed at Doubleview’s field camp where they are photographed, measured and logged by our technical staff and then divided using a diamond bladed saw. One half is placed in a stout bag to form the assay sample that is forwarded securely to the independent analytical lab.  The remaining half core is stored on site where it is available for further examination and sampling. The assay cores are subject to a Chain of Custody routine as they are shipped from camp to a bonded carrier for delivery to the lab.

All core samples are prepared and analyzed at AGAT Laboratories in Calgary, an independent ISO 17025 and ISO 9001 certified facility. Samples are dried, crushed to 70% passing 2 mm, split to obtain a 250 g representative portion, and pulverized to 85% passing 75 µm. Gold, platinum, and palladium are assayed by 30–50 g fire assay with ICP-OES finish. Multi-element analyses (up to 48 elements) are performed by four-acid digestion with ICP-OES/MS, with ore-grade assays applied where required. Selected samples are further analyzed for whole-rock oxides using lithium borate fusion with ICP-OES, and Loss on Ignition is determined separately. Routine quality assurance protocols include insertion of blanks, duplicates, and certified reference materials, ensuring accuracy and reliability of results.

Doubleview maintains a website at www.doubleview.ca.   

Qualified Persons: 

Erik Ostensoe, P. Geo., a consulting geologist, and Doubleview’s Qualified Person with respect to the Hat Project as defined by National Instrument 43-101 Standards of Disclosure for Mineral Projects, has reviewed, and approved the technical contents of this news release. He is not independent of Doubleview as he is a shareholder in the company. 

About Doubleview Gold Corp 

Doubleview Gold Corp. is mineral resource exploration and development company headquartered in Vancouver, British Columbia, Canada. It is publicly traded on the TSX-Venture Exchange (TSXV: DBG), (OTCQB: DBLVF), (WKN: LA1W038), and (FSE: 1D4). Doubleview focuses on identifying, acquiring, and financing precious and base metal exploration projects across North America, with a strong emphasis on British Columbia. The company enhances shareholder value through the acquisition and exploration of high-quality gold, copper, cobalt, scandium, and silver projects-collectively critical minerals utilizing cutting-edge exploration techniques. 

Doubleview's success is deeply rooted in the unwavering support of its long-term shareholders, supporters, and institutional investors. Their ongoing commitment has been instrumental in advancing the company's strategic initiatives. Doubleview looks forward to further collaborative growth and development and continues to welcome active participation from its valued stakeholders as the company expands its portfolio and strengthens its position in the critical minerals sector. 

About the Hat Polymetallic Deposit 

The Hat Deposit, located in northwestern British Columbia, is a polymetallic porphyry project with major resources of copper, gold, cobalt, and the potential for scandium. As one of the region's significant sources of critical minerals, the Hat deposit has undergone targeted exploration and development. The 0.2% CuEq cut-off resource estimate, as of the recently completed Mineral Resource Estimate and the Company's July 25, 2024, news release, is summarized below:  

Average Grade Metal Content
Open Pit Model Hat Resource Category Tonnage CuEq Cu Co Au Ag CuEq Cu Co Au Ag
Mt % % % g/t g/t million lb million lb million lb thousand oz thousand oz
In Pit Indicated 150 0.408 0.221 0.008 0.19 0.42 1,353 733 28 929 2,045
In Pit Inferred 477 0.344 0.185 0.009 0.15 0.49 3,619 1,945 91 2,328 7,575
WordPress Table Plugin

Scandium potential for the Hat Deposit is estimated to be 300 to 500 million tonnes at an average grade of 40 ppm (0.004%) Sc2O3.  “The scandium resource potential is based on the drill holes on the property drilled for (July 25, 2024) maiden resource estimate for other metal content than scandium. The potential quantity and grade are conceptual in nature, there has been insufficient exploration to define a mineral resource, and it is uncertain if further exploration will result in the target being delineated as a mineral resource.”

For further details of the MRE-1, please refer to the Company's July 25, 2024 news release. 

On behalf of the Board of Directors, 

Farshad Shirvani, President & Chief Executive Officer 

 

For further information please contact: 

Doubleview Gold Corp 
Vancouver, BC Farshad Shirvani 
President & CEO 

T: (604) 678-9587 
E: corporate@doubleview.ca 

 

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.  

Certain of the statements made and information contained herein may constitute "forward-looking information." In particular references to the private placement and future work programs or expectations on the quality or results of such work programs are subject to risks associated with operations on the property, exploration activity generally, equipment limitations and availability, as well as other risks that we may not be currently aware of. Accordingly, readers are advised not to place undue reliance on forward-looking information. Except as required under applicable securities legislation, the Company undertakes no obligation to publicly update or revise forward-looking information, whether as a result of new information, future events or otherwise. 

 

Doubleview Gold Corp. (TSXV: DBG) (OTCQB: DBLVF) (FSE: 1D4) ("Doubleview" or the "Company") provides clarification to its news release dated March 2, 2026, announcing the Preliminary Economic Assessment ("PEA") for the Company's 100% owned Hat Project in northwestern British Columbia.

Following publication of the March 2, 2026 news release, Mineit Consulting Inc., the independent engineering firm responsible for the PEA, completed a further review of the application of certain processing cost assumptions relating to the scandium recovery circuit in Scenario B. As a result of this review, the after-tax NPV(5%) for Scenario B at consensus metal prices has been updated to C$7.27 billion from C$6.94 billion and IRR of 19%. The update also results in an increase in Scenario B after-tax NPV(5%) at spot metal prices to C$14.85 billion from C$14.52 billion and IRR of 32%.

The updated Scenario B results further demonstrate the economic contribution of the scandium recovery circuit and increase the difference in after-tax NPV between the base case (Scenario A2) and Scenario B to C$547 million.

The cobalt grade reported in Table 1 of the Company's March 2, 2026 news release was inadvertently shown as 0.78 g/t Co. The correct value is 78 g/t Co, consistent with Table 5 of the release. This discrepancy was limited to the summary table presentation and does not affect the PEA results or conclusions.

These clarifications do not change the overall conclusions of the PEA and further highlight the strong economics of the Hat Project, including the potential value contribution from scandium recovery.

Corrected highlights of the PEA reflecting the updated Scenario B economics are presented below.

NPV:

  • After-tax NPV(5%) of C$6.73 billion and IRR of 23% at Consensus Metal Prices
  • After-tax NPV(5%) of C$13.53 billion and IRR of 39% at Spot Metal Prices

NPV Including scandium and the associated processing circuit:

  • After-tax NPV(5%) of C$7.27 billion and IRR of 19% at Consensus Metal Prices
  • After-tax NPV(5%) of C$14.85 billion and IRR of 32% at Spot Metal Prices

Three processing scenarios were evaluated-Scenario A1 (A1) a Cu-Au-Ag-Co flotation base case using current testwork recoveries1, Scenario A2 (A2), the same base case using expected recoveries1, and Scenario B (B), a Cu-Au-Ag-Co flowsheet with an added hydrometallurgical circuit and scandium recovery circuit, with results indicating the Project is financially attractive even without the scandium component.

Highlights:

  • Robust Project Economics: The PEA demonstrates a high-margin operation with an After-Tax NPV(5%) of C$4.96 billion (A1), C$6.73 billion (A2), or C$7.27 billion (B), and an IRR of 19% (A1), 23% (A2), or 19% (B) at analyst consensus metal prices2. Using a spot-price scenario3, the Project delivers a compelling after-tax NPV(5%) of C$11.05 billion (A1), 13.53 billion (A2), or C$14.85 billion (B) and an IRR of 34% (A1), 39% (A2), or 32% (B).
  • Sensitivity Highlight: Project economics show the greatest leverage to overall metal prices, with NPV (5%) ranging from C$3.2 billion to C$10.2 billion (IRR: 14%-32%) at ±20% on all metals; even under additional +20% CAPEX and +20% OPEX sensitivities, applied on top of a 25% contingency already embedded in the base case, all scenarios deliver IRRs of 16% or better, and Scenario B provides additional scandium oxide upside with NPV(5%) of C$6.5 billion-C$8.1 billion (IRR: 18%-20%) at ±40% metal price.
  • Scale and Longevity: The mine plan supports a multi-decade life of 25 years at a 120,000 tonnes-per-day processing rate, underpinned by a resource base of 609 Mt at 0.43% CuEq4 in the Measured and Indicated categories and 503 Mt at 0.41% CuEq4 in the Inferred category.
  • High-Output Production Profile B: Envisioned as a conventional large-scale open-pit operation, the Project is expected to produce an average of over 74 kt of copper, 254 koz of gold, 376 koz of silver and 2.7 kt of cobalt annually during the first 10 years, with life-of-mine (LOM) average production of 67.6 kt Cu, 217 koz Au, 348 koz Ag, 2.5 kt Co, and 128 tonnes of scandium oxide per year. (NOTE: based on publicly reported 2024 North American cobalt mine production of approximately 3,800-4,000 tonnes (Natural Resources Canada; U.S. Geological Survey), the projected cobalt output is estimated to represent approximately 69% of current regional mined supply).
  • Strategic Importance for Critical Minerals: The Project is positioned as a primary North American source of copper, scandium, and cobalt. With approximately 2.42 billion pounds of copper, 80 million pounds of cobalt and 2,415 tonnes of scandium oxide contained5 in the Measured and Indicated categories, the Project represents an important discovery of critical minerals.
  • Stable, Supportive Jurisdiction: Located in a premier mining district in British Columbia, the Project benefits from a stable regulatory environment. The Company is committed to engaging with local First Nations in a respectful manner and to working toward positive and constructive relationships as the Project advances.
  • Catalyst for Development: The PEA serves as the technical foundation for an immediate transition into a Pre-Feasibility Study (PFS), providing a clear roadmap for early works and permitting activities in 2026 and 2027.

Farshad Shirvani, President and CEO of Doubleview Gold Corp., commented, "The results of this PEA confirm the scale, strength and long-term potential of the Hat Project. Delivering a post-tax NPV(5%) of up to C$6.73 billion and IRR of up to 23% at consensus prices, and even stronger metrics at spot prices, validates years of disciplined exploration and technical work by our team. Hat is demonstrating Tier 1 characteristics with a 25-year mine life, strong annual production profile and meaningful free cash flow generation. Importantly, the Project stands on its own without reliance on scandium, while still preserving significant upside from critical minerals as markets mature. We are excited to advance Hat to Pre-Feasibility and continue building a major Canadian critical metals project."

Doubleview acknowledges that the Project is located on the traditional territories of the Tahltan Nation and the Taku River Tlingit First Nation, and recognizes their enduring relationship to and stewardship of the land and waters. Doubleview is committed to respectful, transparent, and ongoing engagement with First Nations and local communities whose territories overlap the Project area and access routes, with a focus on protecting water and the environment and advancing responsible development.

PEA OVERVIEW

The PEA contemplates a conventional open-pit mine and processing operation with a 25-year mine life at a 120,000 t/d (42 Mt/a) plant throughput. Two processing pathways were evaluated, A1 and its alternative, A2, and B: the first alternative, A, is a Cu-Au-Ag-Co flotation concentrator with two recovery cases based on current metallurgical testwork, and A2, reflecting expected performance (Figure 1); and B, a full circuit that retains the base flowsheet and adds a downstream hydrometallurgical scandium recovery circuit (Figure 2).

The tailings storage facility is a centreline-raised facility built with compacted cycloned sand from tailings underflow, and engineered drainage for stability, with site-contact waters (including seepage and pit dewatering) recycled to the process plant and final closure involving pond drainage and reclamation. The Project is expected to rely on grid power via an extended transmission line.

Tables 1 to 3 summarize the key results of the PEA, including production, operating costs, capital expenditures, and the principal financial metrics; the sections that follow provide additional detail on the underlying assumptions, project design, and study outcomes.

Table 1: PEA Study Summary-Production

Metric Unit Scenario A1 Scenario A2 Scenario B
Mining Summary
Strip ratio t:t 1.60
Production Summary LOM
Average Annual Throughput Mt 42
CuEq Head Grade6, 7 % 0.42
Cu Head Grade % 0.19
Au Head Grade g/t 0.19
Ag Head Grade g/t 0.51
Co Head Grade g/t 77.73
Sc Head Grade6 g/t 28.35
Cu Recovery % 80 89 858
Au Recovery % 66 75 898
Ag Recovery % 53 53 688
Co Recovery % 30 30 788
Sc Recovery % N/A 728
Overall Mass of Tailings to Process9 % N/A 12.5
Year of Production Start of Sc2O38 year N/A 4
Average Annual Cu Production kt 63.6 70.8 67.6
Total Cu Production kt 1,590.5 1,769.4 1,689.9
Average Annual Payable Cu kt 61.7 68.7 65.7
Total Payable Cu kt 1,542.8 1,716.3 1,642.2
Average Annual Au Production koz 161.1 183.1 217.3
Total Au Production koz 4,028.2 4,577.5 5,432.0
Average Annual Payable Au koz 153.1 173.9 207.5
Total Payable Au koz 3,826.8 4,348.7 5,188.6
Average Annual Ag Production koz 271.3 271.3 348.0
Total Ag Production koz 6781.6 6,781.6 8,700.9
Average Annual Payable Ag koz 244.1 244.1 318.6
Total Payable Ag koz 6,103.4 6,103.4 7,965.3
Average Annual Co Production kt 1.0 1.0 2.5
Total Co Production kt 23.9 23.9 62.2
Average Annual Payable Co kt 0.8 0.8 2.3
Total Payable Co kt 19.1 19.1 56.3
Average Annual Sc2O3 Production t N/A 128.4
Total Sc2O3 Production t N/A 3,209.5
Total Sc2O3 Payable t N/A 3,049.0

 

Table 2: PEA Study Summary-Operating Cost

Metric Unit Scenario A1 Scenario A2 Scenario B
Operating Cost
Average Mine Operating Costs C$/t-moved 2.32
Average Mine Operating Costs C$/t-milled 6.03
Processing Operating Cost10 C$/t-milled 7.93 7.93 10.84
Sc2O3 Processing Cost11 C$/kg Sc2O3 N/A 939.55
General & Administrative C$/t-milled 2.56 2.56 2.56
Total Operating Costs C$/t-milled 16.22 16.22 21.92

 

Table 3: PEA Study Summary-Capital Expenditure and Financial Metrics

Metric Unit Scenario A1 Scenario A2 Scenario B
Capital Expenditure
Initial Capital Costs C$M 3,552 3,601 3,828
Sustaining Capital Costs C$M 2,755 2,755 4,006
Closure and Reclamation Cost C$M 503
Financial Metrics
Exchange Rate CAD/USD 1.37
Long Term Copper Price US$/lb 4.88
Long Term Gold Price US$/oz 3,272.60
Long Term Silver Price US$/oz 50.22
Long Term Cobalt Price US$/lb 19.57
Long Term Scandium Oxide Price US$/kg N/A 1,500
Average Annual EBITDA C$M 886 1,071 1,284
Total EBITDA C$M 22,162 26,770 32,101
Average Annual Free Cash Flow (Pre-tax) C$M 756 940 1,104
Free Cash Flow (Pre-tax)12 C$M 18,904 23,511 27,592
Total Provincial Tax (inc. BC Mineral Tax) C$M (4,029) (5,090) (6,019)
Total Federal Tax C$M (1,274) (1,859) (2,308)
Total Taxes C$M (5,303) (6,949) (8,327)
Average Annual Free Cash Flow (Post-tax) C$M 544 662 771
Free Cash Flow (Post-tax)12 C$M 13,601 16,562 19,265
Total Free Cash Flow (Pre-tax)13 C$M 15,352 19,910 23,764
Total Free Cash Flow (Post-tax)12 C$M 10,050 12,961 15,437
NPV 5% (Pre-tax) C$M 7,883 10,576 11,567
NPV 5% (Pre-tax) US$M 5,754 7,720 8,443
IRR (Pre-tax) % 24 29 23
Payback (Pre-tax) years Year 5 Year 4 Year 6
NPV 5% (Post-tax) C$M 4,963 6,727 7,274
NPV 5% (Post-tax) US$M 3,623 4,911 5,309
IRR (Post-tax) % 19 23 19
Payback (Post-tax) Years Year 6 Year 5 Year 7

 

Table 4 shows the Sensitivity analysis using after-tax NPV(5%) and after-tax IRR.

Table 4: Sensitivity Analysis

Variable Case
(%)
Metal Price Scenario A1 Scenario A2 Scenario B
NPV (5%)
C$M
IRR
(%)
NPV (5%)
C$M
IRR
(%)
NPV (5%)
C$M
IRR
(%)
Base Case Consensus forecast 4,963 19 6,727 23 7,274 19
Copper Price -20 US$3.90/lb Cu 3,218 15 4,807 19 5,433 16
Copper Price +20 US$5.86/lb Cu 6,688 23 8,632 28 9,099 22
Gold Price -20 US$2,618.08/oz 3,625 16 5,223 19 5,539 16
Gold Price +20 US$3,927.12/oz 6,289 22 8,222 27 8,996 22
Metal Prices -20 All metal prices 1,708 10 3,165 14 2,993 11
Metal Prices +20 All metal prices 8,118 27 10,233 32 11,444 26
Initial CAPEX +20 Variable per Scenario 4,448 16 6,222 19 6,732 16
OPEX +20 Variable per Scenario 3,660 16 5,438 20 5,591 16
Scandium Oxide Price -40 US$900/kg Sc2O3 6,496 18
Scandium Oxide Price +40 US$2,100/kg Sc2O3 8,050 20

 

MINERAL RESOURCE ESTIMATE

Doubleview Gold Corp announced an update of the Mineral Resource estimate (MRE). This estimate followed the Micon International Ltd. (Micon) Mineral Resource estimate with an effective date of July 17, 2024. This MRE incorporates significant new data from the 2024 and 2025 exploration campaigns, with an effective date of February 4, 2026, and superseded the 2024 Micon estimate.

Table 5: Hat MRE at a 0.2% CuEq Cut-Off Effective February 4, 2026

Mineral
Resource
Classification
Tonnage
(Mt)
Average Grade Metal Content
CuEq
(%)
Cu
(%)
Au
(g/t)
Co
(g/t)
Ag
(g/t)
CuEq
(Blb)
Cu
(Blb)
Au
(Moz)
Co
(Mlb)
Ag
(Moz)
Measured 272 0.44 0.22 0.18 76.26 0.37 2.61 1.11 1.41 35.6 2.17
Indicated 337 0.43 0.21 0.19 76.81 0.39 3.21 1.31 1.81 44.5 2.88
Total M+I 609 0.43 0.21 0.18 76.57 0.38 5.82 2.42 3.22 80.1 5.05
Inferred 503 0.41 0.18 0.19 76.62 0.38 4.57 1.72 2.77 66.2 4.19

 

Table 6: Hat MRE at a 0.2% CuEq Cut-Off as of February 4, 2026, Scandium Oxide Resources

Mineral Resource
Classification
Tonnage
(Mt)
Sc Tonnage1
(Mt)
Average Grade
Sc (g/t)
Metal Content
Sc2O3 2 (t)
Measured 272 34 28.79 1,081
Indicated 337 42 28.76 1,334
Total M+I 609 76 28.77 2,415
Inferred 503 63 28.69 1,996

 

Notes:

1 Scandium tonnages represent 12.5% of the mineralized material by category, reflecting the proportion of tailings expected to be processed through a dedicated scandium leach circuit under current metallurgical design constraints.
2 Scandium oxide metal content have been calculated using the metallurgical recovery of 72% and conversion factor from Sc to Sc2O3 of 1.534.

  • Mineit's Qualified Person, Tomasz Wawruch, FAusIMM, completed the MRE, and has reviewed and approved the technical disclosure related to the MRE contained in this news release. Mr. Wawruch is a senior geology and mineral resource consultant independent of Doubleview. Mr. Gilles Arseneau, PhD., P.Geo., of ARSENEAU Consulting Services Inc., provided an independent review of this MRE.
  • Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
  • The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.
  • Inferred Mineral Resources are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as Mineral Reserves.
  • The Mineral Resource Estimate was prepared in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Definition Standards for Mineral Resources and Mineral Reserves (2014), and CIM MRMR Best Practice Guidelines (2019).
  • The effective date of the MRE is February 4, 2026.
  • Metal contents have been calculated using the following metallurgical recovery factors: Cu = 85%, Au = 89%, Co = 78%, and Ag = 68%.
  • Economic assumptions used include US4.80/lb Cu, US20.00/lb Co, US3,200/oz Au, US46/oz Ag, and a 2% NSR royalty.
  • Mineral Resources are reported within optimized open pit constraints and 0.2% CuEq cut-off grade, based on a C7.93/t milled processing cost and C2.90/t milled general and administrative cost, with a mining cost of C3.01/t plus incremental mining cost increasing by C0.015/t for every bench below the reference level of 1,125 mRL.
  • CuEq calculations do not include scandium. The formula used to calculate CuEq is: CuEq = [(((Ag × 46.0 × 0.68)/31.1035) + ((Au × 3200 × 0.89)/31.1035) + 0.0001 × (Co × 20.0 × 0.78 × 22.0462) + 0.0001 × (Cu × 4.8 × 22.0462 × 0.85))/(4.8 × 22.0462 × 0.85)], where all input variables are expressed in (ppm) and CuEq is expressed in percent (%).
  • Rounding may result in minor variations between individual values and totals; such differences are not considered material to the MRE.
  • Mineral Resource classification reflects the level of geological confidence and satisfies the uncertainty criteria appropriate for exploration and resource development. Additional drilling will be required to reduce uncertainty to the level expected for production planning.
  • The MRE reflects the geological interpretation, drill-hole spacing, and estimation parameters available at the time of modelling. Any additional drilling is expected to influence the current outcome by improving confidence in the estimates and refining the geometry of the mineralized domains.
  • The Mineral Resource results are presented in situ within the optimized pit. Mineralized material outside the pit has not been considered as a part of the current MRE tabulation. Calculations used metric units (metres, tonnes, g/t).
  • A total of 97 diamond drill holes, comprising 49,548 m of core, were incorporated into the Mineral Resource Estimate. All drilling data used in the MRE were subject to standard QA/QC validation prior to inclusion.

PROCESSING SCENARIOS

The PEA evaluates two processing scenarios: (A) a conventional Cu-Au-Ag-Co flotation concentrator at 120,000 t/d (42 Mt/a) with two recovery cases-A1 based on metallurgical testwork completed by Sepro Laboratories (Langley, BC) and A2 reflecting target/expected performance-and (B) a full circuit that retains the base flowsheet and adds a downstream hydrometallurgical scandium recovery circuit.

The concentrator consists of crushing, grinding, flotation, concentrate handling, and tailings management, producing both a saleable approximately 25% Cu concentrate with co-product gold and by-product silver-cobalt credits and a pyrite concentrate enriched in cobalt; in the full-circuit case, the pyrite concentrate is roasted to generate sulphuric acid and a calcine that is then processed to recover cobalt, gold, silver, and copper; after stripping it will be precipitated as a sulphide to be admixed to the copper concentrate to improve grade, with the acid used to leach flotation tailings for scandium recovery, noting that the scandium circuit is a newer chemical process compared with the otherwise industry-standard flowsheet.

Under A1 or A2 (Figure 1), the flowsheet produces a single saleable product-a copper concentrate with payable gold credits; the pyrite concentrate is not treated or marketed in this case and is only processed in B where the hydrometallurgical circuit enables recovery of cobalt (and additional Au-Ag) and supports the scandium circuit (Figure 2), which is planned to be constructed in a phased approach commencing in Year 3 of operations.

Figure 1: Grinding and Flotation Flowsheet; Scenarios A1/A2 Report Copper Concentrate Only, while the Cobalt-Pyrite Flotation Stream Shown Is Included Only in Scenario B

Figure 2: Scenario B Hydrometallurgical Plant Block Flow Diagram, Showing Downstream Treatment of the Cobalt-Pyrite Stream and Flotation of Tailings to Recover Cobalt (and Au-Ag) and Scandium, Including Sulphuric Acid Generation to Support the Scandium Circuit

Table 7 summarizes the head grades, concentrate grades, and overall metallurgical recoveries from early testwork for the full circuit; A1 assumes only the reported recoveries to the Cu-Au concentrate, while the cobalt-pyrite concentrate and downstream recoveries are considered only in B.

Table 7: Attainable Recovery from Testwork

Product Grade Recovery
Copper
(%)
Cobalt
(g/t)
Gold
(g/t)
Silver
(g/t)
Copper
(%)
Cobalt
(%)
Gold
(%)
Silver
(%)
Head Grade 0.21 132 0.34 2.9 - - - -
Copper-Gold Concentrate 25 1160 12 68 80 30 66 53
Cobalt-Pyrite Concentrate 0.30 1605 2 8 5 48 23 15
Combined Concentrates - - - - 85 78 89 68
Tailings 0.05 40 0.05 1.0 15 22 11 32

 

Early metallurgical testwork comprised metallurgical characterization studies under standard laboratory conditions to demonstrate metals recoverability for inclusion in the estimate of CuEq. No attempt was made to optimize flotation conditions, and more advanced flotation testwork was not undertaken. Consequently, the reported metallurgical recoveries are considered conservative, and it is reasonable to expect improvement with further testwork.

A2, assumes improved copper and gold recoveries of 89% and 75%, respectively, reflecting expected performance from comparable Cu-Au porphyry flotation circuits following further optimization and testwork.

Table 8 summarizes the recoveries assumption on each scenario.

Table 8: Net Recovery for Each Scenario

Net Recovery Scenario A1 Scenario A2 Scenario B
Cu Recovery 80% 89% 85%
Au Recovery 66% 75% 89%
Ag Recovery 53% 53% 68%
Co Recovery 30% 30% 78%

 

CAPITAL COST SUMMARY

Table 9 presents the estimated capital cost breakdown for the three evaluated scenarios, separating initial CAPEX from sustaining CAPEX and reporting costs in C$M by major cost area (processing plant, mining, pre-stripping, infrastructure, tailings and water management, Indirects/EPCM, and contingency).

Total initial CAPEX is estimated at C$3,552 million (A1), C$3,601 million (A2), and C$3,828 million (B), reflecting the higher processing plant scope and associated indirects/contingency in Scenario B.

Total sustaining CAPEX is estimated at C$2,755 million (A1/A2) and C$4,006 million (B), with the increase in B driven primarily by the inclusion of the hydrometallurgical plant and scandium recovery circuit within sustaining capital, while mining, infrastructure, and tailings sustaining components remain broadly consistent across scenarios.

Table 9: Capital Cost Summary

Capital Cost Summary Unit Scenario A1 Scenario A2 Scenario B
Initial Capex
Processing Plant (Excl. Hydrometallurgical Plant) C$M 1,609 1,645 1,810
Mining CAPEX C$M 394 394 394
Mining Pre-Stripping C$M 97 97 97
Infrastructure (Power/Water/Roads/Camp)14 C$M 326 326 326
Tailings And Water Management C$M 157 157 157
Indirects + EPCM C$M 258 262 278
Contingency (25%) C$M 710 720 766
Total initial CAPEX C$M 3,552 3,601 3,828
Sustaining CAPEX
Processing Plant (Inc. Hydrometallurgical Plant) C$M 285 285 1,194
Mining CAPEX C$M 811 811 811
Infrastructure (Power/Water/Roads/Camp) C$M 63 63 63
Tailings and Water Management C$M 1,065 1,065 1,065
Indirects + EPCM C$M 142 142 233
Contingency (25%) C$M 390 390 640
Total Sustaining CAPEX C$M 2,755 2,755 4,006
Closure and Reclamation C$M 503 503 503

 

OPERATING COST SUMMARY

Table 10 summarizes the key operating cost and selling terms used in the PEA, reporting unit costs in C$/t moved, C$/t milled, and (where applicable) C$/kg of scandium oxide, together with concentrate transport and selling costs, TC/RC, and payability assumptions.

Average site operating costs are estimated at C$16.22/t milled for Scenario A (concentrate-only) and C$21.92/t milled for B, with the increase in B driven by the addition of hydrometallurgical processing and acid generation (C$3.09/t milled) and scandium oxide processing costs (C$939.55/kg Sc₂O₃).

On a payable metal basis, the study reports C1 cash costs of C$2.4/lb CuEq (A1), C$2.39/lb CuEq (A2), and C$2.89/lb CuEq (B) and AISC of C$2.79/lb CuEq (A1), C$2.78/lb CuEq (A2), and C$3.39/lb CuEq (B), reflecting the combined effects of recoveries, co-product/by-product credits, and the additional operating requirements of the full circuit.

Table 10: Operating Cost Summary15

Operating Cost Summary Units Value
Average Mining Cost C$/t-moved 2.32
Processing Cost - Up to Concentrate production (Scenario A) C$/t-milled 7.93
Hydrometallurgical + Acid Generation (Scenario B) C$/t-milled 3.08
Scandium Oxide processing (Scenario B) C$/Kg Sc2O3 939.55
G&A C$/t-milled 2.56
Total Operating Cost C$/t-milled 21.92
Cu-Au concentrate product
Transport and selling C$/DMT 95.90
TC Cu-Au Concentrate C$/DMT 77.00
Refining Cost- Cu C$/lb 0.11
Refining Cost- Au C$/oz 6.85
Refining Cost- Ag C$/oz 0.48
Refining Cost- Co C$/lb 0.16
Payable - Cu % 97
Payable - Au % 95
Payable - Ag % 90
Payable - Co % 80
Metal Production on-site (Scenario B)
Payable - Au % 97
Payable - Ag % 97
Payable - Co % 97
C1 / cash cost (Scenario A1/A2/B) US$/lb CuEq payable 1.75 / 1.74 / 2.11
AISC (Scenario A1/A2/B) US$/lb CuEq payable 2.04 / 2.03 / 2.47

 

ECONOMIC RESULTS

Table 11 summarizes the key economic assumptions and resulting financial metrics for Scenarios A1, A2, B, including the long-term price deck, cash flow generation, taxation, and discounted valuation at a 5% discount rate. Using an exchange rate of 1.37 CAD: 1.00 USD and long-term prices of US$4.88/lb Cu, US$3,272.60/oz Au, US$50.22/oz Ag, and US$19.57/lb Co (and US$1,500/kg Sc₂O₃ for B), the Project generates average annual EBITDA of C$886 million (A1), C$1,071 million (A2), and C$1,284 million (B). On a post-tax basis, NPV(5%) is estimated at C$4,963 million (A1), C$6,727 million (A2), and C$7,274 million (B) with corresponding post-tax IRRs of 19%, 23%, and 19%, and post-tax payback in Year 6 (A1), Year 5 (A2), and Year 7 (B). Total post-tax free cash flow is estimated at C$10,050 million (A1), C$12,961 million (A2), and C$15,437 million (B), reflecting the higher cash generation under the improved recovery case (A2) and the additional revenue streams in Scenario B, partially offset by the added capital and operating requirements of the hydrometallurgical and scandium circuits.

Table 11: Financial Metrics Consensus Metal Prices

Metric Unit Scenario A1 Scenario A2 Scenario B
Financial Metrics
Exchange Rate CAD/USD 1.37
Long Term Copper Price US$/lb 4.88
Long Term Gold Price US$/oz 3,272.60
Long Term Silver Price US$/oz 50.22
Long Term Cobalt Price US$/lb 19.57
Long Term Scandium Oxide Price US$/kg N/A 1,500
Average Annual EBITDA C$M 886 1,071 1,284
Total EBITDA C$M 22,162 26,770 32,101
Average Annual Free Cash Flow (Pre-tax) C$M 756 940 1,104
Free Cash Flow (Pre-tax)16 C$M 18,904 23,511 27,592
Total Provincial Tax (Including BC Mineral Tax) C$M (4,029) (5,090) (6,019)
Total Federal Tax C$M (1,274) (1,859) (2,308)
Total Taxes C$M (5,303) (6,949) (8,327)
Average Annual Free Cash Flow (Post-tax) C$M 544 662 771
Free Cash Flow (Post-tax)16 C$M 13,601 16,562 19,265
Total Free Cash Flow (Pre-tax)17 C$M 15,352 19,910 23,764
Total Free Cash Flow (Post-tax)17 C$M 10,050 12,961 15,437
NPV 5% (Pre-Tax) C$M 7,883 10,576 11,567
NPV 5% (Pre-Tax) US$M 5,754 7,720 8,443
IRR (Pre-Tax) % 24 29 23
Payback (Pre-Tax) years Year 5 Year 4 Year 6
NPV 5% (Post-Tax) C$M 4,963 6,727 7,274
NPV 5% (Post-Tax) US$M 3,623 4,911 5,309
IRR (Post-Tax) % 19 23 19
Payback (Post-Tax) years Year 6 Year 5 Year 7

 

Table 12 summarizes the key economic assumptions and resulting financial metrics for A1, A2, B, using spot metal prices.

Table 12: Financial Metrics, Spot Metal Prices

Metric Unit Scenario A1 Scenario A2 Scenario B
Financial Metrics
Exchange Rate CAD/USD 1.37
Long Term Copper Price US$/lb 6.00
Long Term Gold Price US$/oz 5,200.00
Long Term Silver Price US$/oz 90.00
Long Term Cobalt Price US$/lb 25.54
Long Term Scandium Oxide Price US$/kg N/A 1,500
Average Annual EBITDA C$M 1,514 1,775 2,096
Total EBITDA C$M 37,843 44,376 52,391
Average Annual Free Cash Flow (Pre-Tax) C$M 1,383 1,645 1,915
Free Cash Flow (Pre-Tax)16 C$M 34,585 41,118 47,882
Total Provincial Tax (Includes BC Mineral Tax) C$M (7,657) (9,163) (10,732)
Total Federal Tax C$M (3,328) (4,166) (4,963)
Total Taxes C$M (10,985) (13,329) (15,696)
Average Annual Free Cash Flow (Post-Tax) C$M 944 1,112 1,287
Free Cash Flow (Post-Tax)16 C$M 23,600 27,789 32,187
Total Free Cash Flow (Pre-Tax)17 C$M 31,033 37,517 44,054
Total Free Cash Flow (Post-Tax)17 C$M 20,048 24,188 28,358
NPV 5% (Pre-Tax) C$M 17,230 21,073 23,258
NPV 5% (Pre-Tax) US$M 12,577 15,382 16,977
IRR (Pre-Tax) % 43 50 40
Payback (Pre-Tax) years Year 3 Year 3 Year 3
NPV 5% (Post-Tax) C$M 11,047 13,526 14,848
NPV 5% (Post-Tax) US$M 8,064 9,873 10,838
IRR (Post-Tax) % 34 39 32
Payback (Post-Tax) years Year 3 Year 3 Year 4

 

SENSITIVITY ANALYSIS

Sensitivity cases were evaluated for the key value drivers using after-tax NPV (5%) and after-tax IRR, including ±20% copper and gold prices, +20% initial capital, +20% operating costs and, for B, a ±40% scandium price sensitivity.

Table 13: Sensitivity Summary (After-Tax NPV(5%) and IRR)

Variable Case
(%)
Metal Price Scenario A1 Scenario A2 Scenario B
NPV (5%)
(C$M)
IRR
(%)
NPV (5%)
(C$M)
IRR
(%)
NPV (5%)
(C$M)
IRR
(%)
Base Case Consensus forecast 4,963 19 6,727 23 7,274 19
Copper Price -20 US$3.90/lb Cu 3,218 15 4,807 19 5,433 16
Copper Price +20 US$5.86/lb Cu 6,688 23 8,632 28 9,099 22
Gold Price -20 US$2,618.08/oz 3,625 16 5,223 19 5,539 16
Gold Price +20 US$3,927.12/oz 6,289 22 8,222 27 8,996 22
Metal Prices -20 All metal prices 1,708 10 3,165 14 2,993 11
Metal Prices +20 All metal prices 8,118 27 10,233 32 11,444 26
Initial CAPEX +20 Variable per Scenario 4,448 16 6,222 19 6,732 16
OPEX +20 Variable per Scenario 3,660 16 5,438 20 5,591 16
Scandium Oxide Price -40 US$900/kg Sc2O3 6,496 18
Scandium Oxide Price +40 US$2,100/kg Sc2O3 8,050 20

 

Overall, the sensitivity analysis demonstrates that the Project's after-tax economics remain positive across the tested ranges, with the greatest variability in after-tax NPV(5%) and IRR driven by simultaneous changes in the overall metal price deck. Changes to copper and gold prices individually have a meaningful but smaller effect, while +20% initial CAPEX and +20% OPEX reduce value but do not eliminate Project attractiveness in any of the evaluated scenarios. Scenario B shows additional exposure to scandium oxide price, with after-tax NPV(5%) varying within a narrower range relative to the broader multi-metal price cases, indicating that scandium provides incremental upside while the base-case Cu-Au Project remains financially robust on its own.

PERMITTING, RISKS, AND NEXT STEPS

Permitting and Environmental

Permitting Status

The permitting process will be supported by the continuation of environmental baseline studies, progression of engineering designs, and the initiation of socio-economic and cultural baseline studies.

Due to the anticipated rate of resource extraction, it is expected that the Hat Project will be subject to both federal and provincial impact assessment pathways, so submission to both the Impact Assessment Agency of Canada (IAAC) and British Columbia Environmental Assessment Office (B.C. EAO) for their review is currently anticipated. Agency determination will decide the appropriate level of agency collaboration under the existing cooperation agreement for the Hat Project to acquire a provincial Environmental Assessment Certificate (EAC) and/or federal Decision Statement.

The company will also submit a Joint Mines Act and Environmental Management Act Application through the B.C. Major Mines Office. Additional federal authorizations, including Fisheries Act approvals and compliance with Metal and Diamond Mines Effluent Regulations (MDMER), and applicable provincial permits will be obtained concurrently with other assessment and permitting steps. This will not only support protection of the immediate environment through the life of the Project but also respect the rights of First Nations and promote social and economic wellbeing for local communities.

Tailings and Water Management

The Tailings Storage Facility (TSF) includes a perimeter dyke primarily constructed from compacted cycloned sand. This material will be sourced from the coarse underflow of tailings processed through an on-site cyclone plant. Using the centreline raise method, the dam is designed to be free-draining, lowering the phreatic surface to facilitate geotechnical stability. During operations, seepage from the TSF will be directed to the process plant as reclaim water. Upon closure, the supernatant pond will be drained, and the tailings and dam surfaces will be reclaimed with a granular trafficability layer, followed by a growth medium and native revegetation.

The water management strategy prioritizes the reuse of site-impacted water, directing TSF water, contact water from the waste rock storage facilities, and open-pit dewatering to the process plant for use as make-up water.

Key Risks and Opportunities

Project-wide

  • Tailings Storage Facility:
    • The location and geometry of the TSF are subject to refinement following geotechnical investigations of the potential site areas. Similarly, the anticipated availability of cycloned sand and the storage requirements for the facility may be adjusted once laboratory testing of the tailings is conducted.
    • The integration of this future site-specific data presents a significant opportunity to optimize the TSF design.
  • Mineral Processing:
    • Limited metallurgical and comminution data introduce uncertainty in equipment sizing and operating cost inputs; however, early results indicate the ore should be amenable to conventional Cu-Au flotation, with potential upside from improved recoveries and reduced reagent consumption through optimization.
    • The scandium circuit is less mature and is sensitive to acid economics and hydrometallurgical performance, but offers meaningful value upside if recoveries, product quality, and operating stability are confirmed at larger scale.
  • Mine Design:
    • Pit slope design criteria and mine scheduling are subject to elevated uncertainty due to the limited geotechnical database, including incomplete definition of structural controls, rock mass variability, and groundwater conditions. This creates downside risk to slope angles, strip ratio, and operating conditions if adverse structures or hydrogeology are encountered; however, it also provides a clear opportunity to materially improve design confidence and potentially optimize slope geometry, mine sequencing, and dewatering requirements through focused data acquisition and updated analyses.
  • Capital Cost estimates:
    • As a PEA-level estimate, capital costs remain subject to the inherent uncertainty of a preliminary design basis and limited engineering definition; however, significant effort was undertaken to develop the estimate using a defined scope, preliminary equipment sizing, and factored/benchmark-based costing with appropriate indirects and contingency. This work provides a credible foundation for decision-making at this stage while also highlighting clear opportunities to optimize capital intensity through further engineering definition, value engineering, and targeted trade-off studies (e.g., comminution configuration, tailings strategy, infrastructure/power, and construction execution approach).
  • Scandium specific:
    • Scandium provides strategic upside given its small, concentrated global supply base and the growing premium placed on secure, qualified supply, but it carries higher execution and commercial risk due to limited scale-up testwork (variability, impurity control, reagent intensity), added residue-management and permitting complexity, and uncertainty around product specifications, pricing, and customer qualification.

Next Steps

  • Resource:
    • The Company is advancing the Project toward Pre-Feasibility by upgrading confidence in the current Mineral Resource estimate and improving definition of mineralization within the proposed mine plan area. The program will prioritize infill drilling to support conversion of Inferred Resources to Indicated (and, where appropriate, Measured), together with step-out drilling to test extensions of known mineralization and provide improved geological continuity for next-stage mine design, scheduling, and economic evaluation.
  • Waste facilities:
    • Field investigations will be conducted at potential TSF and waste rock storage sites to characterize subsurface conditions and identify suitable borrow materials for construction. These efforts will be supported by site-specific geotechnical and geochemical characterization of the tailings and waste rock. These data sets will inform a TSF design update to a Pre-Feasibility Study (PFS) level of engineering, encompassing an optimized siting and technology trade-off study.
  • Metallurgy:
    • Complete a comprehensive metallurgical testwork program on representative samples including comminution testwork (Bond Work Index, abrasion index, and related grindability tests) and metallurgical variability + locked-cycle flotation testing to define an optimal process flowsheet, mass balance, and optimized reagent scheme, and to produce samples for concentrate dewatering and preliminary smelter marketing.
    • Progress the scandium work through targeted hydrometallurgical optimization including pulp density, free acidity/acid consumption, SX staging and extractant concentration, followed by an integrated pilot trial on bulk samples to validate scandium recovery, product quality, and circuit operability.
  • Mine Design:
    • A phased geotechnical program is recommended that includes re-analysis of existing boreholes (re-logging and detailed structural mapping, including oriented-core interpretation where available), establishment of geotechnical domains, targeted drilling and field mapping to confirm discontinuity sets and persistence, and hydrogeological data collection to constrain pore pressures and inflows. These data will support updated kinematic assessments and slope design analyses, refinement of inter-ramp and overall slope angles, and improved inputs to mine planning, risk management measures, and capital/operating cost estimates.
  • Capital Costs Estimation:
    • As the Project advances to PFS, the estimate will be progressively refined by advancing engineering to a higher level of definition, updating quantities and vendor inputs for major equipment and packages, tightening indirects and construction productivity assumptions, and executing focused optimization and constructability reviews to reduce contingency and improve overall cost confidence.

NI 43-101 DISCLOSURE, QUALIFIED PERSONS, AND CAUTIONARY STATEMENTS

Qualified Persons

The scientific and technical information in this news release has been reviewed and approved by the following Qualified Persons, each with respect to the matters within their area of expertise, (as defined under NI 43-101):

  • Tomasz Wawruch, FAusIMM, Senior Geology and Mineral Resource Consultant of Mineit Consulting Inc. (responsible for the Mineral Resource estimate).
  • Andrew Carter, EUR ING, B.Sc., CEng., MIMMM (QMR), MSAIMM, SME, of Magister Metallurgy (responsible for metallurgical studies and recovery processes).
  • Shervin Teymouri, P.Eng., Mining Engineer of Mineit Consulting Inc. (responsible for project management, mining engineering, capital and operating cost estimates, and financial analysis).
  • Andre de Ruijter, P.Eng., of Mineit Consulting Inc, (process design, process capital and operating cost lead).
  • Franky Li, P.Eng., of EMM Consulting Pty Ltd (responsible for tailings management and TSF design, tailings capital and operating cost).
  • Jayesh Rami, P.Eng., Infrastructure Engineer of Sacre-Davey Engineering Inc. (responsible for project infrastructure).

Qualified Person Review

The scientific and technical information contained in this news release has been reviewed and approved by Shervin Teymouri, P.Eng., a Qualified Person as defined under National Instrument 43-101. Mr. Teymouri is a mining engineer and is independent of the Company.

Preliminary Economic Assessment Cautionary Statement

The Preliminary Economic Assessment (PEA) for the Hat Project is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The PEA provides a conceptual mine plan and is based on low-level technical and economic assessments that are insufficient to support an evaluation of the economic viability of the Project or to establish Mineral Reserves. There is no certainty that the results of the PEA will be realized. Further exploration and site-specific engineering studies are required before a higher level of confidence can be established for the Project's economics.

The economic analysis in the PEA is based on several assumptions including, but not limited to, long-term metal prices, foreign exchange rates, metallurgical recoveries, and capital and operating cost estimates. These assumptions are subject to significant risks and uncertainties, and actual results may differ materially from those projected. Readers are cautioned not to place undue reliance on the PEA or the forward-looking information contained in this release.

Forward-Looking Information

Certain of the statements made and information contained herein may constitute "forward-looking information" within the meaning of applicable Canadian securities laws. Often, these forward-looking statements can be identified using words such as "anticipates," "believes," "continue," "estimates," "expects," "forecasts," "intends," "plans," "projected," or the negatives thereof or variations of such words and phrases. Forward-looking statements in this news release include, but are not limited to, statements with respect to: the results of the Preliminary Economic Assessment for the Hat Project; the estimation of mineral resources; anticipated annual production of copper, gold, cobalt, and scandium; the after-tax NPV and IRR of the Project; forecasted AISC and Total Cash Costs; estimated initial and sustaining capital costs; the timing of a Pre-Feasibility Study; the timeline for permitting milestones and construction decisions; planned early works and infrastructure upgrades; and the Company's ability to maintain strong community and First Nations partnerships.

Forward-looking statements are based on a number of assumptions that management considers reasonable at the time they are made, including assumptions regarding: the future prices of copper, gold, cobalt, and scandium; foreign exchange rates; metallurgical recoveries; the cost of essential consumables; and the geopolitical and regulatory climate in British Columbia. However, such statements involve known and unknown risks and uncertainties which may cause actual results to differ materially. These risks include but are not limited to inaccurate estimation of mineral resources; volatility in metal prices; the results of future exploration and development activities; liquidity and financing risks; failure to obtain necessary permits; geotechnical conditions; and changes in applicable mining laws. The PEA is preliminary in nature and includes Inferred mineral resources that are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. Except as required by law, the Company undertakes no obligation to update or revise forward-looking information as conditions change.

Non-GAAP Financial Measures

The Company has included certain performance measures in this news release that are not specified, defined, or determined under Generally Accepted Accounting Principles (GAAP). These non-GAAP measures are common in the mining industry but do not have standardized definitions and may not be comparable to similar measures presented by other issuers. Readers should not consider these measures in isolation or as a substitute for performance measures prepared in accordance with GAAP.

  • Total Cash Costs: The Company calculates total cash costs as the sum of mining, processing, refining and transport, G&A, and royalty costs. Cash costs per unit are calculated by dividing the total cash costs by the payable Copper Equivalent (CuEq) units.
  • All-In Sustaining Cost: AISC is a non-GAAP financial measure comprising of total cash costs, sustaining capital expenditures to support ongoing operations, and closure costs. AISC per unit is calculated by dividing the total all-in sustaining costs by the payable CuEq units.
  • Sustaining Capital: This is a supplementary financial measure reflecting cash-basis expenditures expected to maintain operations and sustain production levels over the life of the mine.

About Doubleview Gold Corp.

Doubleview Gold Corp., a mineral resource exploration and development company based in Vancouver, British Columbia, Canada, is publicly traded on the TSX Venture Exchange (TSXV: DBG), the OTCQB (DBLVF), the Berlin Stock Exchange (GER: A1W038), and the Frankfurt Stock Exchange (1D4). Doubleview identifies, acquires, and finances precious and base metal exploration projects in North America, particularly in British Columbia. The Company increases shareholder value through the acquisition and exploration of quality gold, copper, cobalt, scandium, and silver properties-collectively critical minerals-and through the application of advanced, state-of-the-art exploration methods. Doubleview's portfolio of strategic properties provides diversification and mitigates investment risk.

About Mineit Consulting Inc.

Mineit Consulting Inc. (Mineit) is an independent mining engineering consulting company providing specialized expertise in project management, geological modelling, Mineral Resource estimation, mining engineering, metallurgical, and process engineering. Mineit led and prepared the Hat Project MRE and PEA, with assistance from other engineering firms, for the Hat Project in accordance with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Definition Standards on Mineral Resources and Reserves.

For further information, please contact:

Doubleview Gold Corp
Vancouver, BC

Farshad Shirvani
President & CEO

Institutional Line: (604) 607-5470
T: (604) 678-9587
E: corporate@doubleview.ca

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

Certain of the statements made and information contained herein may constitute "forward-looking information." In particular references to the Mineral Resource Estimate and future work programs or expectations on the quality or results of such work programs are subject to risks associated with operations on the property, exploration activity generally, equipment limitations and availability, as well as other risks that we may not be currently aware of. Accordingly, readers are advised not to place undue reliance on forward-looking information. Except as required under applicable securities legislation, the Company undertakes no obligation to publicly update or revise forward-looking information, whether as a result of new information, future events or otherwise.


Notes:

1 Early metallurgical testwork comprised metallurgical characterization studies under standard laboratory condition to demonstrate metals recoverability for inclusion in the estimate of Cu(eq). No attempt was made to optimize flotation conditions and more advanced flotation testwork was not undertaken. Consequently, the reported metallurgical recoveries are considered conservative and it's reasonable to expect improvement with further testwork.
2 Analyst consensus prices as of February 20, 2026: Au US$3.272/oz; Cu US$4.88/lb; Ag US$50.22/oz; Co US$19.57/lb; Sc2O3 US$1,500/kg.
3 Spot prices as of February 25, 2026: Au US$5,200/oz; Cu US$6.00/lb; Ag US$90.00/oz; Co US$25.50/lb; Sc2O3 US$1,500/kg.
4 CuEq calculations do not include scandium.
5 Scandium tonnages represent 12.5% of the mineralized material by category, reflecting the proportion of tailings expected to be processed through a dedicated scandium leach circuit under current metallurgical design constraints. Scandium oxide metal content has been calculated using the metallurgical recovery of 72% and conversion factor from Sc to Sc2O3 of 1.534. The full scandium content has not been taken into economic evaluation at this time, as current market pricing for scandium lacks sufficient transparency and firmness to support a reliable valuation. Additional scandium in future assessments is considerable upon receipt of binding purchase commitments that establish a defined price. Until such time, scandium reporting to tailings may be preserved for potential recovery when market conditions in North America or Europe provide clearer price visibility.
6 Scandium not used for CuEq calculation.
7 CuEq grade calculation assumes metal process of Copper US$4.80/lb, Gold US$3200/troy oz, Silver US$46/troy oz, Cobalt US$20/lb. The CuEq formula is: CuEq = [(((Ag × 46.0 × 0.68)/31.1035) + ((Au × 3200 × 0.89)/31.1035) + 0.0001 × (Co × 20.0 × 0.78 × 22.0462) + 0.0001 × (Cu × 4.8 × 22.0462 × 0.85))/(4.8 × 22.0462 × 0.85)].
8 Hydrometallurgical and Scandium circuit to be constructed after production of copper concentrate starts. Recovery reported consider the complete processing circuit is operational.
9 Scandium tonnages represent 12.5% of the mineralized material by category, reflecting the proportion of tailings expected to be processed through a dedicated scandium leach circuit under current metallurgical design constraints
10 Processing cost of C$7.93/t-milled for up to concentrate production, and additional C$3.08/t-milled for hydrometallurgical and acid generation plant for Scandium processing. Energy price C$0.07/kWh assuming grid power.
11 Treatment cost to produce Scandium Oxide from the tailings, without considering acid cost (produced on site).
12 Free Cash Flow during production periods only.
13 Total life of mine Free Cash Flow, including initial capital costs and closure.
14 Capital cost estimate Infrastructure includes the required power infrastructure include the extension of the transmission line (~150 km), switching stations and mine main substations (~C$140 million).
15 Energy price C$0.07/kWh assuming grid power.
16 Free Cash Flow during production periods only.
17 Total life of mine Free Cash Flow, including initial capital costs and closure.